At HRM Florida, a kitchen cabinet installation job takes about one week to complete. That covers prep, installation, adjustments, and a final walkthrough for a standard kitchen. Timelines vary with kitchen size, cabinet type, and the condition of your walls and floors, so ask any contractor for a written schedule before work begins.
Why the Installation Timeline Matters
Your kitchen is the hardest room to live without. You lose your sink, counter space, and storage while the work is underway, so a clear timeline helps you plan meals, protect your belongings, and schedule other trades. A contractor who gives you a firm number and explains what could change it is easier to trust than one who says “it depends.”
What Happens During a One-Week Cabinet Installation
A typical week at HRM Florida follows the order below. Exact days shift with each kitchen’s size and layout.
Stage | What Happens | Typical Timing |
Prep and removal | Clear the space, remove old cabinets, check walls and floors | Day 1 |
Upper cabinets | Mark level lines and mount wall cabinets | Days 1–2 |
Base cabinets | Set, level, and secure base units and islands | Days 2–3 |
Doors, drawers, hardware | Hang doors, fit drawers, install pulls and soft-close hinges | Days 3–4 |
Trim and finishing | Crown moulding, toe kicks, filler panels, touch-ups | Days 4–5 |
Final walkthrough | Check alignment and door swing, fix small adjustments | Days 5–7 |
What Affects How Long Cabinet Installation Takes
- Kitchen size and layout. More cabinets, corners, and islands mean more installation time.
- Cabinet type. RTA (ready-to-assemble) cabinets arrive flat-packed and must be built first, while pre-assembled cabinets arrive ready to hang.
- Condition of the room. Uneven walls, damaged drywall, or worn flooring may need repair before cabinets go in.
- Demolition. Removing old cabinets and haul-away adds time.
- Plumbing and electrical. Moving a sink, dishwasher, or outlets must be coordinated with other trades.
- Delivery and lead times. Installation cannot finish until every box, door, and piece of trim is on site.
- Design changes. Switching layouts or finishes mid-project is the most common cause of delays.
How Countertops, Tile, and Flooring Fit Into the Schedule
Cabinets are often one part of a larger project, and the order of work matters. Countertops are measured after the cabinets are installed, then fabricated, so they arrive after the cabinet job ends. Homeowners planning countertop installation in Kendall should expect templating once the cabinets are set, then a separate installation date. Backsplash tile follows the countertops. Whether flooring goes in before or after cabinets depends on your design, so settle that early.
Planning a Bigger Renovation
The one-week figure applies to the cabinet installation job itself. A full remodel takes longer, and the timeline depends on the scope. Because HRM Florida handles kitchens, bathrooms, flooring, and tile under one team, the trades can be scheduled in the right order. Examples:
- Kitchen renovation services in Orlando can combine cabinets, countertops, tile, and floors in one plan.
- Bathroom remodelling in Orlando covers custom vanities, showers, and tile.
- Floor renovation in Miami includes new installation and refinishing.
- Tile installation in Hialeah covers backsplashes, floors, and showers.
If you are comparing kitchen remodel contractors in Hialeah, ask whether cabinets, countertops, and tile are handled by the same team. That usually means fewer scheduling gaps.
How to Choose the Right Cabinet Installer
When comparing cabinet installation contractors in Miami or looking for cabinet installation in Kendall, ask:
- How many days will installation take, and will you put it in writing?
- Is demolition and haul-away included?
- Who coordinates countertop templating and installation?
- Does the written estimate include all costs, with no hidden add-ons?
- What warranty covers the workmanship?
- Can I see photos of completed projects?
If you are searching for the best renovation company in Hialeah, look past star ratings. Ask for a clear schedule and a written estimate, and visit a showroom if you can. HRM Florida has showrooms in Hialeah, Orlando, and Pompano Beach, and offers a free consultation and a written estimate upfront.
How to Keep Your Installation on Schedule
- Confirm measurements before cabinets are ordered.
- Inspect the delivery as soon as it arrives.
- Clear the kitchen before day one.
- Choose hardware and finishes before work starts.
- Set up a temporary kitchen with a microwave, cooler, and basic supplies.
- Keep one point of contact for questions and changes.
Frequently Asked Questions
How long does kitchen cabinet installation take?
At HRM Florida, about one week. Other contractors may quote different timelines, so confirm yours in writing.
Can I use my kitchen during installation?
Only in a limited way. Plan a temporary setup, because the sink and stove may be unavailable at times.
Are countertops installed in the same week?
Usually not. Countertops are measured after the cabinets go in, then fabricated and installed on a later date.
Do RTA cabinets take longer to install?
They can, because they must be assembled first. Properly built RTA cabinets perform well.
What causes installation delays?
Late deliveries, wall or floor repairs, plumbing or electrical changes, and design changes after work begins.